treatment

TREATMENT

1. Product is transferred to Holding tank and kept for 24 H
for gravity discharge of water.
2. Water is then discharged to T3 (water is then transferred
to an authorized disposal facilities
3. Product is then tested for water content
4. If needed, Product is then transferred to T2 Dehydration
tank with vacuum and heated up to 160 to 170°C
5. finished product is then transferred to T4